For High Rate
Discharge Applications
Edward P. Rafter, PE
Power Engineering, Inc.
Kansas City, KS 66103
This paper will show
calculations based on the present method in IEEE 450 and a proposed alternative
method, including the resulting difference in the calculated capacity, for
flooded lead acid and valve regulated batteries in high-rate discharge
applications.
Introduction
In performing a comparison
between the two methods, it is necessary to ask What is the motivation for this exercise? Is it purely an academic
interest? Is the disparity such that the method used will provide misleading or
incorrect information?
The possible implications
of a difference in the calculated capacity of a battery due to the method used
goes beyond an inconsistency between two published industry standards.
The performance of annual
load testing and the subsequent calculation of battery capacity are used by
many to proactively manage their stationary battery plant. In a critical power
application, this information is essential not only in planning against the
replacement of the battery, but also in providing a degree of comfort that the
system will perform to its maximum potential if required to do so.
This proactive approach is
quite evident in mission critical businesses relying on Uninterruptible Power
Systems (UPS). In the application of an UPS the potential impact from the
failure of a battery could have a significant financial impact to the business
enterprise. Many businesses are adopting this proactive approach in the support
of their UPS battery plants and are including annual load testing as part of an
aggressive maintenance program.
An UPS battery is by design
intended for a High Rate Discharge. For the purposes of the comparison between
the present and proposed methods, batteries associated with UPS load tests were
selected. The analysis compares test data for different discharge rates between
5 minutes and 1 hour, 20 minutes.
Test Procedure
Before we compare the data, it is important to review the test
methodology used. A typical method for testing an UPS battery includes the
following:
1)
Isolate the critical
load. This may be accomplished by placing the load on a Maintenance Bypass source. This Bypass
is a wrap around path to the UPS.
2)
Place a resistive load
bank on the output of the UPS.
3)
Establish full load on
the UPS. For example an UPS module rated 150 kVA, 120 kW would be loaded to its
maximum capacity of 120 kW.
4)
While monitoring the
battery, including overall DC voltage, current and individual cell voltages,
fail the AC input to the UPS.
5)
During the battery
discharge, the overall DC voltage, current and individual cell voltages are
monitored and the data recorded for later analysis.
6)
The test is terminated
either when the UPS reaches its pre-set shutdown voltage or by restoring the
normal input.
The load may not
necessarily be at the full load rating of the module. Performing a load test at
less than the rated capacity of the system is sometimes employed and is often
referred to as a Performance Test.
The procedure outlined above will remain essentially the same. The length of
the discharge may be longer than at full load. On this point it should be noted
that the UPS may shutdown at a higher voltage during a prolonged battery
discharge. This provision is often available where Valve Regulated Lead Acid
(VRLA) batteries are used to assure that the battery is not discharged for a
prolonged period.
Data Analysis
Existing
Method for Calculating Capacity
The existing method for
calculating the capacity as per IEEE 450 is based on the following formula:
% Capacity at 25 OC
(77 OF) = [Ta/Ts] x 100
where
Ta is actual time of test to specified terminal voltage
Ts is rated time to specified terminal voltage
Procedurally this includes
the following:
A)
Average the kW load
applied to the battery for the duration of the load test. This is essentially
the product of the measured battery terminal voltage and current averaged over
time.
B)
Calculate the kW per
cell (or monoblock). The average measured kW for the battery is then divided by
the number of cells in the string.
C)
Adjust the average kW per
cell for the initial electrolyte temperature. The method presented in IEEE 450
recommends using a Temperature Correction Factor to adjust the discharge power
rate prior to testing. It is suggested that the power rate should be divided by the temperature correction
factor to determine the test load. In AC testing of UPS battery systems the
measured load is adjusted after the
completion of the test. The average measured kW is multiplied by the Temperature Correction Factor. Battery Capacity
is calculated based on the adjusted power rate.
D)
The calculation is the
actual Time at the adjusted test rate
divided by the rated Time for the
load applied. The manufacturers discharge tables for the battery model are used
to determine the published time at the adjusted rate to reach system end
voltage (ex. 1.67 VPC). This may require interpolating for times that are not
provided in the tables.
The following sample
calculation sheet illustrates this procedure.

Capacity
Calculation Sheet
Figure 1
Proposed
Method for Calculating Capacity
The proposed method
suggests that a discharge curve should be constructed for the cell under test.
The curve is constructed for a predetermined end voltage. The curve is plotted
using the manufacturers published discharge tables for the cell model.
Using the steps outlined in
A) through C) above, the adjusted discharge rate is calculated for the capacity
calculation using the curve as follows.
a) A horizontal line representing the adjusted discharge
rate (Watts) is drawn to an
intersection on the curve. This line may extend beyond the curve or fall short
of the curve depending on the actual discharge time.
b)
If the horizontal line
stops on the curve, the capacity is 100%. A vertical line drawn from the point
of the curve representing the adjusted rate to an intersection on the
x-coordinate (Time) will yield the
published time to the selected end voltage.
c)
If the horizontal line
falls short of the curve a vertical line is erected up to an intersection on
the discharge curve. A second horizontal line is drawn from the intersection
point to the vertical scale representing Watts
d)
If the horizontal line
extends beyond the curve, a vertical line is erected down to an intersection on
the discharge curve. A second horizontal line is drawn from the intersection
point to the vertical scale representing Watts
The calculated capacity is the Watts
(Wa) identified with the actual run time divided by the Watts (Wt) derived from the discharge curve multiplied by 100.
% Capacity = [Wa/Ws] x 100, where temperature
compensation has been factored into the ‘actual’ Watts.
The following graph depicts a discharge curve constructed in this
manner.
Discharge
Curve
Figure 2

Comparative Analysis
A comparative analysis was
performed of several Flooded Lead Acid and VRLA batteries. The following table
represents four (4) Flooded and three (3) VRLA batteries chosen for different
discharge rates from a nominal 5 minutes to 1 hour, 20 minutes. The data is
organized in ascending order for the Actual Time recorded for each test
sequence.
Capacity Calculations Using Existing Method
|
|
Time (Min.) |
|
||||
|
Flooded |
Published Time |
Actual Time |
Capacity |
|
|||
|
C&D XT4LC-15 |
6.3 |
5.5 |
87% |
|
|||
|
C&D XT2LCP-25 |
12 |
10.5 |
88% |
|
|||
|
EXIDE 4DX-17B |
9.9 |
12.5 |
126% |
|
|||
|
C&D XT1LC-35 |
28.52 |
30 |
105% |
|
|||
|
C&D XT4LCP-13 |
31.2 |
32 |
103% |
|
|||
|
|
|
|
|
|
|||
|
|
|
|
|
|
|||
|
Valve Regulated Lead Acid |
Published Time |
Actual Time |
Capacity |
|
|||
|
C&D LS6-50 |
13.5 |
12 |
89% |
|
|||
|
JC UPS12-370 |
14.2 |
15 |
106% |
|
|||
|
JC
UPS12-310FR |
64.4 |
80 |
124% |
|
|||
Table 1
Capacity Calculations Using Proposed Method
|
|
Power (Watts) |
|
|
|
|
Flooded Cell |
Published Watts |
Actual Watts |
Capacity |
||
|
C&D XT4LC-15 |
2967 |
2906 |
98% |
||
|
C&D XT2LCP-25 |
3725 |
3644 |
98% |
||
|
EXIDE 4DX-17B |
2720 |
2962 |
109% |
||
|
C&D XT1LC-35 |
3820 |
3926 |
103% |
||
|
C&D XT4LCP-13 |
1240 |
1265 |
102% |
||
|
|
|
|
|
||
|
|
|
|
|
||
|
Valve Regulated Lead Acid |
Published Watts |
Actual Watts |
Capacity |
||
|
C&D LS6-50 |
176 |
167 |
95% |
||
|
JC UPS12-370 |
340 |
355 |
104% |
||
|
JC
UPS12-310FR |
80 |
102 |
128% |
||
Table 2
Calculated Capacity Comparison
|
Battery
Model |
Existing
Capacity Calculation Method |
Proposed
Capacity Calculation Method |
Percent
Deviation |
Flooded
|
|
|
|
|
C&D XT4LC-15 |
87% |
98% |
- 11% |
|
C&D XT2LCP-25 |
88% |
98% |
- 10% |
|
EXIDE 4DX-17B |
126% |
109% |
+ 17% |
|
C&D XT1LC-35 |
105% |
103% |
+ 2% |
|
C&D XT4LCP-13 |
103% |
102% |
+ 1% |
|
|
|
|
|
Valve Regulated Lead Acid
|
|
|
|
|
C&D LS6-50 |
89% |
95% |
- 6% |
|
JC UPS12-370 |
106% |
104% |
+ 2% |
|
JC
UPS12-310FR |
124% |
128% |
- 4% |
Table 3
The data suggests that the
calculated capacity for the Flooded cells and VRLA batteries at the five and
ten minute rate is significantly different between the two methods. However,
the calculated capacity using the existing method produced battery capacities greater than the proposed method in
four (4) of the samples. The calculated capacity for the Exide battery was
significantly greater using the existing method. A review of the curve
developed for this cell indicates a very steep slope related to the Watts vs.
Time computation.
Differences in the
calculated capacity of 1 to 2 percent may be due to inaccuracies in the
interpolation or curve construction process.
It was expected that a
convergence in the calculated capacity for each method should occur for the low
rate discharges exceeding one hour. The data suggests that the disparity is
less as the discharge rates decrease.
Conclusion
The test data indicates
that there is a difference in the calculated capacity of a battery between the
existing and proposed methods for high rate discharges. The difference is more
evident in discharge rates less than 30 minutes. The curve construction related
to the proposed method may yield results that are counterintuitive to the
expected figures. Since the curve is constructed from the manufacturers
supplied discharge data, these unusual results could be due to discrepancies in
the data provided. This is particularly true where an interpolation is the
primary source for the curve construction.
Additional comparative
analysis is indicated. Manufacturers data should include both tabular and
graphical information to help resolve potential inaccuracies.
There still exists a school
of thought that in a UPS application, the point when the battery can no longer
support the rating of the system for 80% of the specified time is when the
battery should be considered for replacement. Therefore the calculation of
battery capacity may be a moot point. As noted above, some calculation is still
required to adjust the load for temperature. It is also clear that given the
above method of testing, the actual load on the UPS may vary significantly due
to factors such as the output voltage setting on the UPS and the test
personnel’s ability to adjust the resistive load bank.
Other arguments contend
that where the Existing Method for
capacity calculation is used, an allowance should be made for the sizing
calculations, which allow an aging factor and must not be overlooked when
performing such calculations. Often the testing company does not have that
information at hand.
Now that we have explored
an alternate method for calculating battery capacity, the industry has produced
an atmosphere of doubt in the testing methodology and the conclusions of
individuals using the existing method. A consensus is mandatory to not only
address an inconsistency in the present standards, but to also alleviate these
doubts and provide direction for those conscientious users who seek to
effectively manage their critical systems.
Bibliography
IEEE Std. 450-1995. IEEE “Recommended Practice for Maintenance, Testing and
Replacement of Vented Lead-Acid Batteries for Stationary Applications.”
IEEE Std. 485-1997. IEEE “Recommended Practice for Sizing Lead-Acid Batteries
for Stationary Applications.”
Acknowledgements
Brian Thornton of Power
Engineering, Inc., for help in organizing and analyzing data.
Jim McDowall, SAFT America, for input on the contents of this paper.